Disputes & Tribunal Cases

4 published court/tribunal decisions across 1 managed property

Cases from NCAT, Supreme Court, Land & Environment Court, and other NSW courts and tribunals involving properties managed by Cityhome Strata Management Pty Ltd.

Raysons Constructions Pty Ltd v The Owners – Strata Plan No 87003

Building defect

SP87003 · 4-8 ANGAS STREET MEADOWBANK, MEADOWBANK

BUILDING AND CONSTRUCTION — Home Building Act 1989 (NSW) — strata building — breach of statutory warranties — limitation period for breach of statutory warranties — whether breach of warranty becomes apparent in last 6 months of warranty period — distinction between defect and breach of statutory warranty — onus of proof for extension — type of knowledge required — whether defect is a major defect — Home Building Act 1989 (NSW) ss 3B, 3C, 18B, 18E, 48K

20 Oct 2026
Read decision [2026] NSWCATAP 324 →

The Owners – Strata Plan 87003 v Raysons Constructions Pty Ltd

Building defect

SP87003 · 4-8 ANGAS STREET MEADOWBANK, MEADOWBANK

APPEAL — question of law — Civil and Administrative Tribunal — proceedings for breach of statutory warranties implied by Home Building Act 1989 (NSW) in residential building work — six year warranty period — Owners Corporation commenced proceedings four months after expiry of six year period — whether proceeding commenced in time — Senior Member found Owners Corporation commenced within further six month period authorised by s 18E(1)(e) because breaches only became apparent in last six months of warranty period — internal appeal — Appeal Panel overturned findings of fact and found proceedings not commenced in time — whether inconsistency on the face of Senior Member’s reasons was a slip — whether Appeal Panel’s construction of reasons involved error of law BUILDING AND CONSTRUCTION — residential building work — Home Building Act 1989 (NSW), s 18E — construction of provision authorising commencement of proceedings in six months after expiry of six year warranty period — whether plaintiff bears onus of establishing facts so as to fall within s 18E(1)(e) — nature of awareness needed to be established in order to fall within section — significance of commencement of proceedings being jurisdictional

25 Feb 2025
Read decision [2025] NSWSC 66 →

Raysons Constructions Pty Limited v The Owners - Strata Plan No 87003

Other

SP87003 · 4-8 ANGAS STREET MEADOWBANK, MEADOWBANK

COSTS – Calderbank letter – whether offer an adequate compromise – whether offeree not acting unreasonably in rejecting offer

8 Aug 2024
Read decision [2024] NSWCATAP 156 →

Source: NSW Caselaw. Only published decisions are shown. Many disputes are resolved privately or through mediation and will not appear here. A case involving a managed property does not necessarily reflect on the manager's performance.